When to Remove Concrete Forms?


Installing concrete is not nearly as easy as it seems. It takes more effort and time plus a bit of calculation, so for that, you need to see the common mistakes you are making and other people too and how you can avoid them by doing it correctly. There is a massive preparation of material and things and drafting the plan before starting the concrete project.

Formwork represents a box or casting mold (like a container) where fresh concrete is poured and compacted.

All the things from making the plan of the concrete and then purchasing the items of the project and then comes the quantity of those items plus you need to identify the area which area should be the better and ideal to make the construction. Plus, you need to note the weather forecast and placement process, tools, and accessories you will need. There is a tip that if you are doing this project for the second, you may be using the old tools and things, even the plans. Still, you need to check the area you will work on when you use one project for one specific time and site; that is not necessarily true for the other sites. So take a deep calculative note on the site you are trying to work on.

So, when to Remove Concrete Forms?

How long should concrete cure before removing forms?

The earliest time to remove concrete forms is:

  • Concrete forms on Walls and columns can be removed after about 24-48 hours
  • Concrete forms on Slabs can be removed after 3-4 days. The average Shuttering removal time for the slab is 3 days.
  • Soffits and props that support slabs under 15 feet can be removed after 1 week.
  • Props that support slabs above 15 feet, beams, and arches under 20 feet, can be removed after 2 weeks.
  • Props that support beams and arches over 20 feet can be removed after 3 weeks.

 

Concrete forms can be removed based on cement type:

  • Type I cement ASTM C 150 after 7 days
  • Type II cement ASTM C 150 after 10 days
  • Type III cement ASTM C 150 after 3 days
  • Type IV or V cement ASTM C 150 after 14 days
  • C 845, C 1157 ASTM C 595, cements: Number of days varies.
Mark Brown

Mark Brown

Mark Brown is a construction engineer from California who has been working as an independent contractor and writer for the past 15 years. From 2022 onwards, Mark has also been contributing author of home repair articles at nimblefreelancer.com. Read more on Mark Brown's biography page. Contact Mark: mark@nimblefreelancer.com